Short answer: when a label converter moves a press, the risk is not the transport. It is every day the press is not printing. A relocation has to fit the customer's transport slot and restart date, so it must be planned as a production project, with enough engineers on site at the same time to work in parallel.

Field note by Christos Kioupis, ATLAS Technical Support.

The situation

A label converter in Turkiye had to move a digital label press to a new location. The transport slot was fixed and the window between dismantling and the date the press had to print again was short. Every extra day meant orders waiting.

What made it harder

The main body of the press alone weighed around two tonnes. The first assumption was that it could travel largely in one piece. It could not. It had to be dismantled fully, and that changed the plan: more hours, more parts to track, more risk of delay.

A modular press is built frame first, then units, doors and covers. That makes it easier to service over its life, but taking it apart and putting it back together takes several days of specialist work, not a few hours.

How we met the window

One engineer working in sequence would not have made it. ATLAS brought in extra engineers from both our Greek and our Turkish teams and put them on one plan: who dismantles which unit, who labels and stages the parts, who rebuilds what at the new site. Work ran in parallel instead of one step after another, and the press went back into production within the customer's window.

Three lessons from the floor

1.     Staging. Every part that comes off is labelled, packed and placed in the order it goes back on. Reassembly speed is decided during disassembly.

2.     Transport. Weight, access, lifting and route are checked before the first screw comes out, not on the day.

3.     Focus. The relocation team does only the relocation. Mixing it with other service calls is how a few days become two weeks.

What a converter should plan for

•        The restart date first, then the transport slot, not the other way round.

•        The new site ready before the move: floor, space, power and compressed air checked against the press requirements.

•        Enough engineers booked for the same days, so work runs in parallel.

•        A print-quality check and sign-off before the press goes back into production.

•        Stock to cover your customers while the press is down.

ATLAS engineers in Greece and Türkiye work as one team. We plan and run relocations end to end: site check, staged dismantling, transport, rebuild and restart, sized to your production window. 


Start the conversation with us https://www.innvestio-group.com/en/#contact 


FAQ

How long does it take to relocate a digital label press?

Plan for several days of specialist work plus transport. A modular press is dismantled and rebuilt unit by unit. More engineers working in parallel shorten the downtime.

Can a label press be moved in one piece?

Usually not. Weight, access and the way the press is built mean most relocations need full or partial dismantling. Assuming a one-piece move is the most common planning mistake.

How do you keep downtime short when the transport window is tight?

Fix the restart date first, prepare the new site before the move, stage every part in reassembly order, and put enough engineers on the job at the same time.